Solar PV
Industry

Stora Enso Solar PV

Client:
Carbon Shift (Equans)
Location:
Belgium
Year:
2025
Key project data
Rated power:
1.4 MVA
Voltage:
150 kV
Contributors
John Joy
Electrical Engineer
Philippe De Rua
Electrical Engineer

Introduction

Equans has delivered a 1.4 MVA rooftop solar installation at Stora Enso’s Langerbrugge paper mill in Ghent. To secure compliance with the Belgian Transmission System Operator (TSO) Elia’s Type B grid code requirements for Power Park Modules (PPMs), Enersynt was engaged to oversee the technical grid integration process, to perform the required power system studies, and to deliver the electrical simulation models to Elia.

Project Background

Stora Enso operates the Langerbrugge Mill, a major producer of recycled fibre materials. To further strengthen its sustainability strategy, the company opted to utilise previously unused roof areas for photovoltaic generation, contributing directly to regional renewable energy targets in Flanders.

Role of Enersynt

Enersynt supported Carbon Shift (Equans) in achieving Elia’s grid connection approval through the following activities:

Electrical Power Systems Modeling

Our engineering team built comprehensive RMS and EMT models of the PV installation using DIgSILENT PowerFactory and PSCAD. These models incorporated detailed inverter representations and formed the foundation for subsequent compliance assessments and studies.

Grid Compliance Studies

Enersynt performed a full suite of studies to demonstrate adherence to Elia’s Type B PPM criteria. This included static simulations to evaluate reactive power capability, load flow analyses to verify equipment loading and voltage levels, and dynamic RMS simulations to examine frequency response, fault-ride-through behaviour, and reactive current injection during voltage dips. Inverter parameters were refined throughout the process to ensure alignment with Elia’s technical expectations.

Stakeholder Coordination 

To streamline project execution, Enersynt collaborated closely with the inverter manufacturer to define model requirements and validate performance outcomes. We also supported Equans in interface meetings with Elia and in completing the Type B data questionnaire and overall grid compliance submission package, incorporating results and parameters from the compliance studies.

Testimonials

“At Equans, we believe that the energy transition starts with decisive collaboration. Thanks to Enersynt’s expertise, we were able to install a high-performing PV system for Stora Enso and meet Elia’s stringent Type B grid compliance requirements."

Michael Catrysse, Project Manager, Carbon Shift (Equans)

Conclusion

The successful completion of the grid compliance studies, supported by close coordination with Equans, ensured a smooth approval process with Elia. Beyond delivering a technically robust and reliable outcome, the project also contributes meaningfully to the region’s renewable energy objectives. It reflects Enersynt’s commitment both to ensuring client success and to advancing the broader transition toward sustainable, low carbon energy systems.

Projects

Case studies

Learn more about our services from a selection of our references
Solar PV
Industry

Stora Enso Solar PV

Equans has delivered a 1.4 MVA rooftop solar installation at Stora Enso’s Langerbrugge paper mill in Ghent. Enersynt performed the power system studies to secure compliance with Elia’s Type B grid code requirements for Power Park Modules (PPMs).
Wind

Hai Long

The Hai Long offshore wind farm has a production capacity of 1044 MW and is one of the first large scale offshore wind farms to be realized in Taiwan. Enersynt provided high-voltage engineering expertise throughout various stages of the project.
Featured Project
Battery

BESS Harmignies

BESS Harmignies is a 76 MW / 300 MWh battery storage project that enhances stability and flexibility on the Belgian transmission grid. Enersynt supported Energy Solutions Group as Electrical Owner’s Engineer throughout design, construction, and commissioning.
R&D
HVDC

Cordoba

The CORDOBA research project aimed to deepen academic and industry understanding and knowledge of offshore hybrid grids while developing essential calculation tools and models for planning, operating, and investing in hybrid offshore systems.
Solar PV

Luxembourg PV

Situated in the Luxembourg province, Wallonia, Belgium, the Diodi solar farm is a planned 40MW PV installation set to be connected to the Elia grid. Initially designed for 70kV operation, the connection will be upgraded to 110kV post-2030.
Wind

TwinHub

The TwinHub floating offshore wind farm, located approximately 16km off the coast of Hayle in Cornwall within the Wave Hub test site, represents a groundbreaking demonstration project.
Transmission

Efficiency assessment transmission projects

Together with AFRY, Enersynt has been entrusted by the ACM with assessing TenneT's high voltage transmission projects to ascertain their adherence to various objectives and efficiency standards.
Hydrogen

Neptune H2opZee

The H2OpZee project represents a pioneering effort in offshore hydrogen technology, developed jointly by Neptune and RWE. The project envisages the offshore production of hydrogen fed by an offshore wind farm with a nominal capacity of 525 MW.
Battery

Deux-Acren

Corsica Sole has developed a 50MW/100MWh battery energy storage system (BESS) in Belgium. Enersynt was entrusted with ensuring compliance with the Elia Type C grid code requirements for Storage Park Modules (SPMs).
Wind

Northwester 2

The Northwester 2 offshore wind farm is located in the North Sea, off the Belgian coast. The grid connection of the wind farm is realized through an offshore high voltage substation which is connected to Elia’s Offshore Switch Yard (OSY) to export the energy to shore.

Let’s start a new project together

We can tell stories about our past projects all day long but would love to hear about yours